Everglades Restoration Plan

The Department of the Army, US Army Corps of Engineers (USACE), South Atlantic Division, Jacksonville District has a requirement for construction of the C-11 Impoundment and Mitigation Area A as part of the Broward County Water Preserve Areas (BCWPA), one of the elements of the Comprehensive Everglades Restoration Plan (CERP).

Solicitation Summary

The Department of the Army, US Army Corps of Engineers (USACE), South Atlantic Division, Jacksonville District has a requirement for construction of the C-11 Impoundment and Mitigation Area A as part of the Broward County Water Preserve Areas (BCWPA), one of the elements of the Comprehensive Everglades Restoration Plan (CERP).

Solicitation in a Nutshell

Item

Details

Agency Department of the Army, US Army Corps of Engineers (USACE), South Atlantic Division, Jacksonville District
Solicitation Number W912EP25R0005
Status Pre-RFP
Solicitation Date 03/12/2025
Award Date 09/2025 (Estimate)
Contract Ceiling Value $500,000,000
Competition Type Undetermined
Type of Award Other
Primary Requirement  Other Construction Services
Duration  1947 days
Contract Type  Firm Fixed Price
No. of Expected Awards N/A
NAICS Code(s):
237990

Other Heavy and Civil Engineering Construction
Size Standard: $45.0 million annual receipts except $37.0 million annual receipts for Dredging and Surface Cleanup Activities

Place of Performance:
  • Broward County, Florida, United States
Opportunity Website: https://sam.gov/opp/f9d5531a4f424d98a6d3f276c3375056/view

Background

N/A

Requirements

  • The Broward County Water Preserve Area (BCWPA), Contract 2 project consists of a portion of the overall C-11 Impoundment project. Contract 2 consists of construction of dam and levee embankment, a mitigation area, water control structures, environmentally sensitive area (ESA) systems, lake backfill, drainage conveyance, ancillary features, and associated clearing, grubbing, planting, borrow, and material processing.
  • Contract 2 is the first of two construction phases (combined with future Contract 3) to complete the overall C-11 Impoundment component of the BCWPA project. The overall completed C-11 Impoundment will be an above-ground earthen reservoir targeted to have a total storage of 4,600 acre-feet with an effective interior area of approximately 1,053 acres and a normal pool water storage depth of approximately 4.7 ft.
  • The Contract 2 dam embankment (D-511) will have an approximate height of 15ft (crest elevation of 18.8 ft NAVD88). The Contract 2 portion of D-511 embankment will include roughly 4,800 ft of slurry wall along the southern alignments between stations 111+00 to 146+00 (east) and stations 204+00 to 218+00 (west). The slurry wall will be 41 ft tall (EL 6.0 ft NAVD88 to EL -35.0 ft NAVD) with a typical width of 2.5 ft.
  • The proposed Mitigation Area ‘A’, is located north of the impoundment. It will 113 acres of wetland marsh. Water levels within the mitigation area will fluctuate approximately 1.0 ft above average ground elevation (5.3 ft NAVD88). The levees surrounding the mitigation area will have an approximate height of 3 ft (crest elevation of 7.3 ft NAVD88).
  • Contract 2 includes 12 total Water Control Structures:
    • Gated Culverts S-506A, S-508B, S-508D, and S-511
    • Ungated Culverts S-500A, S-505E, S-506B, S-508A, and S-509
    • Fixed, Broad-crested Weirs S-505B, S-505C, and S-505F
  • There are two environmentally sensitive areas (ESAs) which are to be protected during construction and ultimately excluded from the project by means of embankment alignment. The ESAs will be protected from disturbance during construction and will be avoided by completed project features.
  • Contact 2 includes a requirement to backfill the existing Central Lake and an existing borrow area. These features are existing quarry pits estimated to be up to 55 feet deep and filled with water. Backfill of the Central Lake and Borrow Area will primarily consist of onsite muck material. However, the Contractor will be provided approximately 10,800 cubic yards of stockpiled lime rock aggregate, located adjacent to SW 26th Street and the proposed construction staging area, which is approved to be placed in Central Lake.
  • Contract 2 will require continuous stormwater management and conveyance of an approximate two square-mile drainage area north of the project site, which flows southward through the project site, plus any stormwater generated within the Contract 2 limits for the duration of the contract. Since stormwater flows will ultimately need to pass south through the future Contract 3 project limits for discharge into the C-11 Canal, stormwater management will include the following control requirements:
    • Stormwater system will convey a 100-year storm to the existing A/5 Canal outfall at the C-11 Canal.
    • Contractor will construct a temporary shallow drainage diversion ditch from the eastern C-511 Canal to the existing A/5 canal. The diversion ditch will be located along the boundary between the Contract 2 and Contract 3, in a zone of temporary construction limit for future resumption by others.
    • Contractor must not construct S-505F broad-crested weir until the eastern section of C-511 and the temporary diversion ditch to the existing A/5 canal are complete.
  • Other project features and activities include clearing, grubbing, planting, borrow, material processing, boat ramps, soil cement embankment armoring, emergency stockpiles, instrumentation and monitoring stations, wetland preservation/protection, erosion control, and debris disposal.

How can GDIC Help?

As a consulting firm that specializes in helping companies prepare winning proposals for government contracts, GDIC can provide a wide range of services to help offerors prepare their C2E proposal, including capture management, proposal writing, proposal management, and proposal review. GDIC can also provide training and support to help offerors understand the technical and administrative requirements outlined in the solicitation, and can provide guidance on how to structure the proposal to maximize its chances of success.

Our business development and proposal professionals have several decades of experience and expertise in construction proposals and contracts for government. By working with GDIC, offerors can increase their chances of winning the C2E contract and can position themselves for long-term success in the federal marketplace.